Even though some of the HVAC is not done, we've begun backframing the upstairs, main floor and basement. The backframers are in charge of the little things - boxing duct work, straightening walls, strapping basement walls etc.
Phil, Miguel's footing guy, was in at the start of the week to layout the footings. After pouring, I was able to get Thom in there to form and pour the bench pinning (kind of like underpinning, but poured in one shot to allow for a deeper basement level for the rec room).