Week 22: Stairs

My old friend from Doma stairs, Tony, had his team deliver and install the beautiful three piece, floating stairs.  It's always hard to tell what the full effect of the open riser look will be while it's covered with protection paper, but I think this is going to turn out fantastic!

Week 21: Closing in - aluminum

Now that the stucco is done on the back and sides, George's team was in to install the soffits, fascia and eaves in the same Iron Ore as the window colour.

Week 20: Stucco!

Elton's crew started the Durock EIFS installation this week.  Once set up, they worked quickly to get the polar barrier, ventilated Styrofoam, parging and finish coat completed.  Looking good!

Week 19: More rough-ins, more concrete!

Thom had the difficult task of forming the front steps to withhold the pressure of 7 meters of concrete... and did a fantastic job!  The poured steps are the main landscaping feature on the front, along with the faux retaining wall in the front of the steps to complete the modern look.  

Week 18: Rough-ins and garage

Rough-ins are continuing inside, while Thom came in and poured and finished the garage slab.  Sweet!