After a major clean up inside, Jampa arrived to start the prefinished maple wood floors. I love the natural colour of the wood and though soft, it's going to wear well over time.
Tony did a quick rough in of the plumbing drains early in the week, which meant Kevin could come and start the electrical. We did a walkthrough with Shaun and Amber and made a lot of the key decisions to move things forward. On the outside, the stucco is being applied to the back and sides of the house. The front will be finished with a combination of stone and longboard.
Still no Enbridge, so this little green electric heater is heating the whole house! Mick has finished spraying in the house, so Jampa swung by to install all of the interior hardware.